THE STAR

description of project
Over the past 11 years, PJS Air has been engaged for multiple upgrades of mechanical services in various areas of the casino including:
• 380 hotel rooms
• 3 gaming floors
• the main foyer
• 10 retail and restaurant tenancies
• 10 kitchens – from 2sqm to over 10 large-scale commercial kitchens
• back of house office and facilities
• 5-level carpark system upgrade
Client:
Shape, FDC, Built., Inscope, MPA, Lendlease, MPA, Multiplex, Honeywell
Consultant:
WSP, Bassett, Simpson Kotzman, NDY
Contract:
Construct-only, Design Completion, full Design and Construct
Location:
Pirrama Rd, Pyrmont NSW 2009
Value of Projects:
$14M+
Timeframe:
2010 – current
Client:
Shape, FDC, Built., Inscope, MPA, Lendlease, MPA, Multiplex, Honeywell
Consultant:
WSP, Bassett, Simpson Kotzman, NDY
Contract:
Construct-only, Design Completion, full Design and Construct
Location:
Pirrama Rd, Pyrmont NSW 2009
Value of Projects:
$14M+
Timeframe:
2010 – current
PJS Air scope of works for thIS project

INCLUDING:
- cooling tower installation
- chillers
- all cold shell fitouts for retail area
- new & upgraded gaming & back of house areas
- Quest room upgrades
- general fans, toilet exhausts, stair press fans and carpark fans
- car park ventilation fans on 5 floors of carpark
INSTALLING:
- computer room air- conditioning (CRAC) cold isle units
- complete new variable ref rigerant volume (VRV) systems for general administration offices

REFURBISHING:
- existing and installing new data centres to accommodate site expansion.
PROVIDING:
- ventilation and reconfiguration of the general maintenance workshops.
OUTCOMES
Delivered on time and on budget.