Sydney masonic center

description of project
The venue required the upgrade of existing mechanical infrastructure to provide much improved energy efficiency for this large variable load conference and function centre, and to simultaneously reclaim Net Lettable Area by relocating the mechanical plant and equipment to the roof top.
We worked in a partially live environment for 9 months, with only a 3-month actual shut down. As an architecturally- designed heritage building, the team were aware of the requirements of the building, ensuring all HVAC works were designed around existing structures, reconfiguring duct work and services to utilise existing penetrations as much as possible.
Builder:
Sydney Masonic Center
Consultant:
Practical Sustainability
Contract:
Design and Construct
Location:
66 Goulburn St, Sydney NSW 2000
Value of Project:
$3.3M
Timeframe:
2018-2019
Builder:
Sydney Masonic Center
Consultant:
Practical Sustainability
Contract:
Design and Construct
Location:
66 Goulburn St, Sydney NSW 2000
Value of Project:
$3.3M
Timeframe:
2018-2019
PJS Air scope of works for thIS project

INSTALLING
- the newly released Daikin VRV-AHU handling system which was the largest installation of its kind in Australia at the time.
- new Daikin building management system integrated with a new Innotech BMS to create a multizone economy cycle and various occupancy operation modes
- internal temporary stairs to allow access to the roof whist the
- 6 new air handlers and 65 new fan coils serving several function rooms and the grand hall
- new switchboards
- new grills and 400m of duct work
- large volume enthalpy heat exchangers for outside air and retrofitting air economy cycle operational up to 45,000 ls at peak.

INSTALLING
- the newly released Daikin VRV-AHU handling system which was the largest installation of its kind in Australia at the time.
- new Daikin building management system integrated with a new Innotech BMS to create a multizone economy cycle and various occupancy operation modes
- internal temporary stairs to allow access to the roof whist theinstallation works were carried out
- 6 new air handlers and 65 new fan coils serving several function rooms and the grand hall
- new switchboards
- new grills and 400m of duct work
- large volume enthalpy heat exchangers for outside air and retrofitting air economy cycle operational up to 45,000 ls at peak.

UPGRADING:
- the stair pressurisation system
- smoke handling systems associated with mechanical services
DESIGNING:
- all mechanical services in the building and developing milestones within the program in order to meet the required finish date
- all new roof-mounted air-handling plant and duct work, as well as their construction

REMOVING
- existing central plant and all associated fan coils and replacing these with variable refrigerant volume (VRV) systems.
REPURPOSING
- plant rooms into future potential conference spaces in coordination with the removal of hazardous materials.
OUTCOMES
PJS Air worked flexibly around the client to meet the program.
Nil LTI’s.
Nil defects.
Full building refurbishment completed on time and on budget
