intercontinental hotel, sydney

description of project
The 35-storey building, built in 1982 required the 529 hotel rooms, front-of-house lobbies, the rooftop bar and restaurant and various back of house areas to be refurbished. The client also wanted to replace the existing HVAC systems in each of the hotel rooms, which could operate issue-free for the next 25 years.
The project requires for us to replace the existing HVAC systems in each of the hotel rooms and major plant upgrades. Our initial dilapidation report found the risers supplying chilled and hot water to the rooms were rusted and required replacement. From here we received approval to develop designs to replace 8 existing risers with a single central core located riser and ring main on each quest room level.
Following the initial design, the PJS Air team are permanently onsite for 18 months during the ECI process to ensure the project will be completed on time and to budget. Through the ECI process, the team is gaining a deep understanding of the overall building in order to create a system design which will guarantee operational efficiency and longevity.
Client:
Built.
Consultant:
WSP
Contract:
Design and Construct
Location:
117 Macquarie St, Sydney NSW 2000
Value of Project:
$10M+
Timeframe:
November 2020 (ongoing till 2022)
Client:
Built.
Consultant:
WSP
Contract:
Design and Construct
Location:
117 Macquarie St, Sydney NSW 2000
Value of Project:
$10M+
Timeframe:
November 2020 (ongoing till 2022)
PJS Air scope of works for thIS project

INCLUDED:
- cooling towers
- chillers
- air handling units
- chilled and hot water risers
- BMS System
- MSSB and essential services switchboards
UPGRADING
- related passive fire systems throughout the building.
REDESIGNING:
- 2 plant rooms and the air handling systems to create more serviceable access.

INSTALLING:
- pressure independent control valves to optimise pump efficiency through self-balancing and pressure control
- future service related items including large access doors, permanent access ladders and safety rails around HVAC
- air handlers on the floor rather than suspending them from gantries or the ceilings where possible

INSTALLING:
- pressure independent control valves to optimise pump efficiency through self-balancing and pressure control
- future service related items including large access doors, permanent access ladders and safety rails around HVACequipment for service access
- air handlers on the floor rather than suspending them from gantries or the ceilings where possible

REPLACING:
- 5km of pipe work including replacing chilled and hot water risers from corroded steel to stainless steel and copper
- 24 air handlers in 2 confined plant rooms
- all belt-driven air-handling units with AC and EC direct drive high-efficiency fan motors
- the end-of-life central plant – new chiller & cooling towers
WORKING:
- with an energy consultant to upgrade systems and controls where possible to increase energy efficiency.
translating:
- hand-drawn drawings of HVAC system into CAD drawings.
OUTCOMES
Nil LTI’s.
Delivered efficiently on time and on budget.